A large industrial park located in a tropical coastal region of the Philippines required a reliable circulating water cooling solution for multiple manufacturing facilities. The cooling system serves both central air-conditioning systems and process cooling equipment. Due to the region’s high temperatures, humidity, and salt-laden coastal air, the customer required a corrosion-resistant, low-maintenance solution capable of delivering stable performance year-round.



Challenge


The customer previously operated conventional open cooling towers that suffered from excessive drift loss, unstable outlet water temperatures, and frequent maintenance issues.

Key challenges included:

  • High ambient temperatures ranging from 32°C to 38°C year-round

  • Severe coastal salt-spray corrosion

  • Significant water consumption caused by drift losses

  • Unstable cooling performance during peak summer operation

  • Need for standardized equipment across multiple workshops

  • Limited local maintenance resources

The customer sought a durable and energy-efficient cooling solution that could ensure reliable operation under tropical coastal conditions while minimizing operating costs.


Solution


CASEN supplied nine Closed-Circuit Cooling Towers specifically configured for the local operating environment.

Key design features included:

Enhanced Corrosion Protection
  • Magnesium-aluminum-zinc coated heat exchange coils

  • Additional anti-corrosion protective coating on the tower casing

  • Designed for long-term resistance to coastal salt-spray exposure

Water-Saving Design
  • High-efficiency drift eliminators

  • Drift loss controlled below 0.001%

  • Reduced water consumption and makeup water demand

Intelligent Capacity Control
  • Nine towers arranged into three modular operating groups

  • Variable Frequency Drive (VFD) fan control

  • Automatic cooling capacity adjustment based on thermal load

Simplified Installation & Commissioning
  • Containerized export packaging

  • Complete English installation manuals and drawings

  • Remote commissioning support for local contractors

Reliability Verification
  • 48-hour continuous full-load factory performance testing

  • Simulated high-temperature and high-humidity operating conditions


Results


All nine cooling towers were successfully commissioned on schedule and entered continuous operation without issue.

After 18 months of operation, the customer achieved:

  • 24/7 stable cooling performance throughout the year

  • Zero coil corrosion failures or leakage incidents

  • 34% reduction in cooling water consumption

  • 17% improvement in HVAC cooling efficiency during peak summer operation

  • 40% reduction in local maintenance workload

The successful project led to additional discussions regarding cooling equipment supply for future industrial park expansion phases.


Key Performance Indicators


ItemResult
Quantity Supplied9 Units
Maximum Ambient Temperature38%
Corrosion-Free Operation18 Months
Water Savings34%
HVAC Efficiency Improvement17%
Maintenance Cost Reduction40%



Project Highlights


  • Standardized anti-corrosion cooling tower solution for Southeast Asian coastal environments

  • Modular multi-unit cooling system with intelligent VFD control

  • Proven long-term performance under high-temperature, high-humidity, and salt-spray conditions

  • Remote overseas commissioning and technical support services




Online Message